OFFICE ELECTRICAL FIT-OUT: RAISED FLOORS, LAN SYSTEMS & DETAILED COST ESTIMATES (BOQ) 2025
Are you feeling the immense pressure of an impending Grand Opening? Are you worried that your new office’s electrical system will be a mess of tangled wires, aesthetically unpleasing, or that the network will crash as soon as your staff headcount increases?
With over 20 years of experience providing M&E consultancy and construction services, I have witnessed countless Grade A office projects that were visually stunning in terms of interior design but were absolute “technical nightmares.” Outlets placed in the wrong spots, constant network dropouts, or costs ballooning by 30% due to vague initial estimates.
To ensure your building electrical & M&E installation meets aesthetic standards and is completed at “lightning speed,” the secret lies in precise technical solutions and a transparent Bill of Quantities (BOQ). In this article, KTH Electric will share the process for installing raised floor electrical systems (Floor boxes), LAN infrastructure, and provide a sample BOQ for a 150m² office space.
Raised Floor Electrical Installation & Floor Boxes
Raised floor electrical installation is the method of running wiring beneath a false floor system, using specialized recessed floor boxes to ensure aesthetics and flexibility. The core element is the Drawing Overlay technique to precisely position outlets directly under desks, avoiding hazardous and unsightly exposed wires in walkways.
If gypsum ceilings hide the HVAC system, then the raised access floor is the “sky” for the office electrical system. Installing electricity under a raised floor is an “art” requiring absolute precision.

Table of Contents
The 4-Step Precision Installation Process
Includes 4 steps: (1) Positioning & Overlaying Drawings -> (2) Installing Trunking/Conduit -> (3) Wiring & Labeling -> (4) Installing Floor Boxes & Safety Grounding.
To ensure the system operates smoothly, we apply a strict protocol:
- Step 1: Positioning (Marking) & Drawing Overlay
Before the floor tiles are installed, engineers must perform a Drawing Overlay: Superimposing the M&E electrical drawing over the Furniture Layout. The goal is to ensure the electrical outlet (Floor box) sits perfectly under the desk clearance, avoiding being crushed by table legs or creating hazards. - Step 2: Routing Trunking and Conduit
The wiring system needs protection from pests and compression forces.- Use Electrical Metallic Tubing (EMT) for branch lines.
- Use a wire mesh cable tray system for the main trunk to allow better heat dissipation.
Note: Adhere to cable tray installation guidelines, ensuring standard support clamp spacing of 1.5m, to prevent the system from shifting during floor installation.
- Step 3: Wiring & Labeling
Use high-quality electrical cables (typically CV 2.5mm² – 4.0mm²). Golden Rule: Label both ends of the wire immediately to facilitate future electrical system maintenance. - Step 4: Installing Floor Box & Safety Connections
Use Pop-up or heavy-duty sliding cover Floor Boxes.⚠️ Warning: Never leave wire joints exposed under the raised floor. You must use IP-rated waterproof junction boxes and follow grounding installation procedures to ensure safety against leakage, as office floors are frequently cleaned with water.
Deploying a Stable ELV System (LAN/Tel)
For 2025 office standards, LAN systems must use Cat6/Cat6A cables and be separated from power lines by at least 30cm to avoid Electromagnetic Interference (EMI). Centralized management at the Rack Cabinet via Patch Panels is mandatory for durability and easy upgrades.

The network system is the “backbone” of the office. Many contractors mistakenly run network cables in the same tray as power lines to cut costs, causing signal interference. You need to understand what ELV is to grasp its importance.
Mandatory Technical Standards
- Network Cable: Minimum Cat6 or Cat6A (CommScope/Legrand).
- Anti-interference: Network cables must be at least 30cm away from power lines.
- Rack Management: Use Patch Panels; do not crimp connectors manually and plug directly into the Switch.

If you need detailed costs for this item, please review our ELV installation quotation article.
“Lightning Speed” Construction Strategy (Rolling Shift)
Rolling Shift is a flexible scheduling method: The Day Shift handles silent work (terminations, device installation), and the Night Shift handles noisy work (drilling, cutting, transporting). This optimizes construction time by 200% without violating building noise regulations.

To meet deadlines in Grade A buildings (which typically restrict noisy work to nights), KTH Electric applies the following strategy:
- ☀️ Daytime (Silent Work): Pulling wires, connecting electrical cabinets, installing devices.
- 🌙 Nighttime (Noisy Work): Drilling, cutting, transporting materials.
- 📂 Documentation: Prepare as-built electrical & plumbing drawings and night work permits in advance to avoid interruptions.
4. MATERIAL BILL OF QUANTITIES (BOQ) & PRELIMINARY QUOTE SAMPLE
💡 Cost Reference: The average unit price for a full-package office electrical fit-out (Class B+) fluctuates around 600,000 VNĐ/m². This price includes genuine materials (Cadivi, Panasonic, CommScope) and night shift labor. The total estimated budget for a 150m² office is approximately 91,350,000 VNĐ.
Below is a PROVISIONAL estimate for a 150m² office (30 employees) based on Class B+ office standards.
PART 1: POWER SYSTEM & FLOOR BOXES
The main power supply category, using high-safety materials.
| No. | Item | Specification / Suggestion | Unit | Qty | Amount (VNĐ) |
|---|---|---|---|---|---|
| I | POWER SYSTEM | 28.500.000 | |||
| 1 | Main Power Cable | Cadivi/LS (Ref: How to calculate wire load) | Meter | 150 | 3.750.000 |
| 2 | Outlet Power Wire | Cadivi CV 2.5mm | Meter | 400 | 4.800.000 |
| 3 | Grounding Wire (PE) | Cadivi (See more: What is IT earthing system) | Meter | 300 | 2.400.000 |
| 4 | Floor Box (Pop-up) | Sino/Panasonic (Alloy Pop-up) | Set | 15 | 12.750.000 |
| 5 | 3-Pin Universal Socket | Panasonic Wide | Pcs | 30 | 3.600.000 |
| 6 | Accessories | Tape, Cos terminals | Lot | 1 | 1.200.000 |
PART 2: LAN SYSTEM & DATA CENTER
| No. | Item | Specification | Unit | Qty | Amount (VNĐ) |
|---|---|---|---|---|---|
| II | NETWORK & COMMS | 22.350.000 | |||
| 1 | Network Cable | CommScope Cat6 (Genuine) | Box | 3 | 11.400.000 |
| 2 | RJ45 Modular Jack | CommScope Cat6 | Pcs | 40 | 4.400.000 |
| 3 | Faceplate | Floor box mounted | Pcs | 30 | 1.050.000 |
| 4 | Patch Panel | Patch Panel 24 Port | Set | 1 | 2.500.000 |
| 5 | Rack Cabinet | 10U – D600 (See: Industrial electrical cabinet shell) | Pcs | 1 | 2.000.000 |
| 6 | Patch Cord | Molded 1m-2m | Pcs | 40 | 3.200.000 |
PART 3 & 4: ROUGH-IN MATERIALS & LABOR
| No. | Item | Specification | Amount (VNĐ) |
|---|---|---|---|
| III | ROUGH-IN MATERIALS | 15.500.000 | |
| 1 | EMT Conduit | EMT Phi 20/25 | 5.200.000 |
| 2 | Mesh Tray | W200 – W300 Galvanized | 5.000.000 |
| 3 | Flexible Conduit & Junction Box | Waterproof | 3.300.000 |
| 4 | Supports & Hangers | Threaded rods, clamps | 2.000.000 |
| IV | LABOR & NIGHT SHIFT SURCHARGE | ~ 25.000.000 | |
| TOTAL (Excl. VAT) | ~ 91.350.000 VNĐ | ||
💡 Expert Insight: The average unit price is around 600,000 VNĐ/m². During construction, careful selection of circuit breakers like MCBs matched to the load is crucial to prevent overload. For larger offices, consider installing Low Voltage Capacitor Banks to optimize power factor and avoid utility penalties.
5. Next Steps for You
Do not rush into signing a construction contract without a “tailor-made” BOQ for your specific Layout. Require the contractor to perform Network Signal Testing (Fluke Test) and Fire Safety (PCCC) inspection before final payment to avoid future legal risks.
Every office has a different Layout. To avoid a situation where “the estimate is one thing, and reality is another,” you need a custom BOQ.
Furthermore, upon completion, Electrical Fire Safety Inspection (PCCC) and signal testing are mandatory for the building management to authorize your operations.
🎁 SPECIAL OFFER FROM KTH ELECTRIC
Contact us for a survey this week to receive a support package worth 5,000,000 VNĐ:
- ✅ Free Shop Drawing Design: Overlay of interior and electrical plans.
- ✅ Signal Measurement: Comprehensive Fluke Test Report.
Contact us immediately to receive the detailed Excel estimate file:
KTH ELECTRIC CO., LTD
Services: Electrical Maintenance | M&E Construction | Office Fit-out.
Address: 251 Pham Van Chieu, Ward 14, Go Vap District, Ho Chi Minh City.
Technical Hotline: 0968.27.11.99
Website: kth-electric.com

Mr. Đỗ Tấn Tuấn oversees all content on the kth-electric.com website. Each article is crafted from his extensive expertise, combining reputable reference materials (with specific citations) and his vast practical experience. Readers can fully trust the accuracy and reliability of the information, ensuring that every shared piece of content provides valuable and trustworthy insights.